From Proposal To Reality, A Look Back At LRT3’s 13-Year Journey

After years of construction, project reviews and revised deadlines, the LRT3 Shah Alam Line officially began operations on 29 June 2026, marking a major milestone for public transportation in the Klang Valley.

First proposed in 2013, the project officially commenced in November 2015 with an initial estimated cost of RM9 billion. However, construction was temporarily halted in 2018 following concerns over project costs and financing.

Despite several setbacks, construction reached 99% completion in February 2025 before undergoing further testing and safety commissioning.

The Shah Alam Line now connects Bandar Utama to Johan Setia across 20 stations, with five additional stations previously targeted to begin operations in the second quarter of 2028.

From its initial proposal to its official opening, explore the key milestones that shaped LRT3 through our interactive timeline below.

THE STOLY · TRANSPORT · 2013–2026

LRT3: From proposal to operation

From its first proposal in 2013 to the start of Shah Alam Line services on 29 June 2026, explore the milestones that shaped LRT3.

Bandar UtamaJohan Setia
RM9 billionInitial cost estimate · Nov 2015
99%Construction progress · Feb 2025
20 stationsPhase 1 operations · Jun 2026
5 stationsPhase 2 · targeted opening Q2 2028

At a glance

The project was first proposed in 2013, temporarily halted in 2018 and restructured in 2019. After several revised opening targets, the first 20 stations opened on 29 June 2026, according to the supplied chronology. Five further stations were targeted to open in Q2 2028.

Construction progress

Four reported progress updates; not a complete monthly series.

Jul 2020

33.12%

Jan 2024

91.86%

Jul 2024

95.6%

Feb 2025

99%

How the opening date changed

Original target28 Feb 2024
2023 revision1 Mar 2025
July 2024 forecastQ3 2025
Opening (as reported)29 June 2026

Two phases, 25 stations

Phase 1: 20 stations between Bandar Utama and Johan Setia.

Phase 2: 5 stations — view details

Tropicana, Raja Muda, Temasya, Bukit Raja and Bandar Botanik.

Expected completion: Q4 2027. Expected opening: Q2 2028 (October 2024 report).

Project timeline

Select an event to reveal details and sources.

2013 · PlanningLRT3 route proposed

Prasarana Malaysia announced a proposed LRT3 route to connect the western corridor of the Klang Valley.

Source: wikipedia

September 2015 · PlanningDelivery partner appointed

The Malaysian Resources Corporation Berhad (MRCB) and George Kent consortium was appointed as Project Delivery Partner (PDP).

Source: wikipedia

November 2015 · PlanningProject officially begins

The LRT3 project officially began with an initial estimated cost of RM9 billion.

Source: mot.gov+1

May 2016 · ConstructionEarly works scheduled

Early construction works were scheduled to begin, including works on the route to Johan Setia, Klang.

Source: audit.gov

August 2016 · ConstructionOfficial project launch

The project was officially launched and major construction began that year.

Source: railjournal+1

2018 · ReviewConstruction temporarily halted

Construction was temporarily halted for review following a change of government and concerns over project costs and financing.

Source: wikipedia

February 2019 · ReviewContract model revised

A novation agreement changed the PDP model to a fixed-price contract. MRCB–George Kent became the turnkey contractor, with Prasarana as the project employer.

Source: myrapid.com+1

July 2020 · Construction33.12% complete

Construction was reported to be 33.12% complete, with completion targeted for the end of February 2024.

Source: utusan.com

2023 · ReviewOpening date revised

The opening date was revised to 1 March 2025 from the original target of 28 February 2024.

Source: utusan.com

January 2024 · Construction91.86% complete

Project progress reached 91.86%. The government proposed a phased opening: 20 stations in Phase 1 and the remaining five in Phase 2.

Source: edgeprop

July 2024 · Construction95.6% complete

Physical progress reached 95.6%. Physical works were expected to finish in October 2024, but operations were expected to be delayed until Q3 2025.

Source: utusan.com

October 2024 · ReviewTargets for five remaining stations

The five previously cancelled stations — Tropicana, Raja Muda, Temasya, Bukit Raja and Bandar Botanik — were expected to be completed in Q4 2027 and open in Q2 2028.

Source: berita.rtm.gov

February 2025 · Construction99% complete

Construction was reported to be 99% complete, with system testing and commissioning expected to begin in April 2025.

Source: railjournal

2025–2026 · OperationsTesting and operational readiness

Prasarana/Rapid Rail continued trial runs, safety commissioning and operational preparations ahead of commercial services.

Source: railjournal+1

22 June 2026 · OperationsOpening date announced

Transport Minister Anthony Loke announced that LRT3 would begin operations on 29 June 2026.

Source: berita.rtm.gov+1

29 June 2026 · OperationsShah Alam Line opens

LRT3 began operations, connecting Bandar Utama and Johan Setia through 20 stations.

Source: danainfra.com+2

Primary source: Kronologi Pembinaan LRT 3.pdf, pages 1–2. Reference labels are retained as provided. Facts have not been independently verified; future targets are projections from the document, not current confirmations. The final project cost is not provided.
Adib Mohd

Recent Posts

Meet niko and …: The Japanese Lifestyle Brand Bringing Its Unique Concept To 1 Utama

A little bit of fashion, a touch of homeware and plenty of room for self-expression.… Read More

33 minutes ago

BookXcess @ 118 Mall Is More Than A Bookstore, It’s A Whole Malaysian Neighbourhood!

What happens when a bookstore meets a kampung-inspired neighbourhood? You get BookXcess @ 118 Mall,… Read More

3 hours ago

Starbucks Rewards Turns 15! StarLand Tour Bringing Games, Freebies & Prizes To Malaysia

Starbucks Rewards is turning 15 in Malaysia, and it’s celebrating with a roadshow packed with… Read More

3 hours ago

Tesla’s Driverless Cybercab Makes Its Final Malaysian Stop At Gurney Plaza Until 22 November

Curious about what a driverless car looks like up close? Tesla Malaysia is giving the… Read More

4 hours ago

A Whale Of A Christmas In Penang! The Waterfront Shoppes Brings Festive Fun By The Water

Christmas is arriving by the water! The Waterfront Shoppes (TWS) is bringing a different kind… Read More

4 hours ago

The Capitol Has Arrived In NYC, Hunger Games Cast Serves Fashion And Nostalgia At Premiere

The countdown is almost over, Hunger Games fans! With The Hunger Games: Sunrise on the… Read More

4 hours ago

This website uses cookies.