After years of construction, project reviews and revised deadlines, the LRT3 Shah Alam Line officially began operations on 29 June 2026, marking a major milestone for public transportation in the Klang Valley.
First proposed in 2013, the project officially commenced in November 2015 with an initial estimated cost of RM9 billion. However, construction was temporarily halted in 2018 following concerns over project costs and financing.
Despite several setbacks, construction reached 99% completion in February 2025 before undergoing further testing and safety commissioning.
The Shah Alam Line now connects Bandar Utama to Johan Setia across 20 stations, with five additional stations previously targeted to begin operations in the second quarter of 2028.
From its initial proposal to its official opening, explore the key milestones that shaped LRT3 through our interactive timeline below.
LRT3: From proposal to operation
From its first proposal in 2013 to the start of Shah Alam Line services on 29 June 2026, explore the milestones that shaped LRT3.
At a glance
The project was first proposed in 2013, temporarily halted in 2018 and restructured in 2019. After several revised opening targets, the first 20 stations opened on 29 June 2026, according to the supplied chronology. Five further stations were targeted to open in Q2 2028.
Construction progress
Four reported progress updates; not a complete monthly series.
How the opening date changed
Two phases, 25 stations
Phase 1: 20 stations between Bandar Utama and Johan Setia.
Phase 2: 5 stations — view details
Tropicana, Raja Muda, Temasya, Bukit Raja and Bandar Botanik.
Expected completion: Q4 2027. Expected opening: Q2 2028 (October 2024 report).
Project timeline
Select an event to reveal details and sources.
2013 · PlanningLRT3 route proposed
Prasarana Malaysia announced a proposed LRT3 route to connect the western corridor of the Klang Valley.
Source: wikipedia
September 2015 · PlanningDelivery partner appointed
The Malaysian Resources Corporation Berhad (MRCB) and George Kent consortium was appointed as Project Delivery Partner (PDP).
Source: wikipedia
November 2015 · PlanningProject officially begins
The LRT3 project officially began with an initial estimated cost of RM9 billion.
Source: mot.gov+1
May 2016 · ConstructionEarly works scheduled
Early construction works were scheduled to begin, including works on the route to Johan Setia, Klang.
Source: audit.gov
August 2016 · ConstructionOfficial project launch
The project was officially launched and major construction began that year.
Source: railjournal+1
2018 · ReviewConstruction temporarily halted
Construction was temporarily halted for review following a change of government and concerns over project costs and financing.
Source: wikipedia
February 2019 · ReviewContract model revised
A novation agreement changed the PDP model to a fixed-price contract. MRCB–George Kent became the turnkey contractor, with Prasarana as the project employer.
Source: myrapid.com+1
July 2020 · Construction33.12% complete
Construction was reported to be 33.12% complete, with completion targeted for the end of February 2024.
Source: utusan.com
2023 · ReviewOpening date revised
The opening date was revised to 1 March 2025 from the original target of 28 February 2024.
Source: utusan.com
January 2024 · Construction91.86% complete
Project progress reached 91.86%. The government proposed a phased opening: 20 stations in Phase 1 and the remaining five in Phase 2.
Source: edgeprop
July 2024 · Construction95.6% complete
Physical progress reached 95.6%. Physical works were expected to finish in October 2024, but operations were expected to be delayed until Q3 2025.
Source: utusan.com
October 2024 · ReviewTargets for five remaining stations
The five previously cancelled stations — Tropicana, Raja Muda, Temasya, Bukit Raja and Bandar Botanik — were expected to be completed in Q4 2027 and open in Q2 2028.
Source: berita.rtm.gov
February 2025 · Construction99% complete
Construction was reported to be 99% complete, with system testing and commissioning expected to begin in April 2025.
Source: railjournal
2025–2026 · OperationsTesting and operational readiness
Prasarana/Rapid Rail continued trial runs, safety commissioning and operational preparations ahead of commercial services.
Source: railjournal+1
22 June 2026 · OperationsOpening date announced
Transport Minister Anthony Loke announced that LRT3 would begin operations on 29 June 2026.
Source: berita.rtm.gov+1
29 June 2026 · OperationsShah Alam Line opens
LRT3 began operations, connecting Bandar Utama and Johan Setia through 20 stations.
Source: danainfra.com+2