COVID-19, Worker’s Shortage, Delay New Sri Aman Hospital Construction — Aaron Dagang

SIMANGGANG (Sarawak), Aug 21  — Completion of the RM180.8 million Sri Aman Hospital, which was scheduled to be operational by June next year, will be further delayed for at least another six more months due to several unavoidable circumstances, said Deputy Health Minister II Datuk Aaron Ago Dagang today.

He said work on the hospital was now 83 percent completed, and work on the project was delayed due to, among the others, the COVID-19 pandemic, resulting in construction work to be at a standstill for four months and the return of the 500 foreign workers, who are from China and Indonesia, back to their respective countries.

“Now the contractor has to depend entirely on the local workforce, which is not easy to get. They called for 290 local workers, but only 82 came to work,” he told reporters after visiting the site today.

However, he said, the contractor had assured him that the project would be completed by February next year.

Work on the hospital, to be equipped with 1,310 rooms and 108 beds, started in 2016. It has the potential to become a leading health facility for residents in the surrounding areas, including Lubok Antu, Simunjan, and Betong.

The project had been approved in 2007 and the first phase of clearing and piling work on the 20.6-hectare site was completed in August 2013.

Sources:  BERNAMA

Adib Mohd

Recent Posts

IZIPIZI Is Now in Malaysia and Your Eyewear Game Will Never Be the Same

Bonjour, Malaysia! Say hello to IZIPIZI, the Parisian eyewear brand that’s finally made its debut… Read More

6 hours ago

Kuala Lumpur Convention Centre Brings 20 Years of Summit Expertise to Centre Stage for 46th ASEAN Summit

KUALA LUMPUR, 15 May 2025 – The Kuala Lumpur Convention Centre (the Centre) is honoured… Read More

7 hours ago

50 Malaysian Hospitals Named Among World’s Best in 2025

Malaysia just flexed its healthcare muscle. In the latest World's Best Hospitals 2025 list by… Read More

10 hours ago

Free Museum Day in Malaysia: Explore 19 Museums for Free on 18 May 2025

Love history, culture, and a good freebie? Then mark your calendars for 18 May 2025,… Read More

1 day ago

INTAN and Huawei Malaysia Unite to Drive Future-Ready Public Sector with Digital Leadership Push

In a landmark step towards modernising Malaysia’s public sector, the National Institute of Public Administration… Read More

1 day ago

Fuel Up, Feel Better: Shell Malaysia and CARiNG Pharmacy Join Forces to Bring Healthcare to Your Pit Stop

In a groundbreaking move to redefine the petrol mart experience, Shell Malaysia has announced a… Read More

1 day ago

This website uses cookies.